4421 City of Fulton 2nd St bridge

Image
Backfilling bent 2 First beam arrives 8:10am Continue with setting box beams  Second to last beam Last box arrived at noon Finished setting beams at 3:15pm

4421 City of Fulton 2nd St Bridge

Image
End bent 1 Getting set up to place box beams Bent 2 is ready to go Unloaded first box beam at 9:43am Continue to set beams Finished setting beams at 12:45

4421 City of Fulton 2nd St bridge

Image
Concrete pour for back walls bent 1 Concrete pour for back walls bent 2

4421 City of Fulton 2nd St Bridge

Image
Mixing products for the UHPC UHPC employee checking to see if we have enough slump (spread) to pour Start pouring UHPC at bent 2 First hole had a leak under precast box Continue with bent 2 pour Continue with pour at bent 1 Finished pour 2:00pm

4421 City of Fulton 2nd St bridge

Image
Bent 1 is ready for precast concrete substructure units Placing precast substructures for bent 1 Bent 1 complete  Start setting precast substructures for bent 2