Backfilling bent 2 First beam arrives 8:10am Continue with setting box beams Second to last beam Last box arrived at noon Finished setting beams at 3:15pm
End bent 1 Getting set up to place box beams Bent 2 is ready to go Unloaded first box beam at 9:43am Continue to set beams Finished setting beams at 12:45
Mixing products for the UHPC UHPC employee checking to see if we have enough slump (spread) to pour Start pouring UHPC at bent 2 First hole had a leak under precast box Continue with bent 2 pour Continue with pour at bent 1 Finished pour 2:00pm
Bent 1 is ready for precast concrete substructure units Placing precast substructures for bent 1 Bent 1 complete Start setting precast substructures for bent 2