4421 City of Fulton 2nd St Bridge Get link Facebook X Pinterest Email Other Apps May 31, 2023 Waiting on asphalt trucks. Set waterproofing membrane on bridge deck Start placing 2nd lift of base asphalt Read more
4421 City of Fulton 2nd St Bridge Get link Facebook X Pinterest Email Other Apps May 31, 2023 Ready for asphalt placement Start placing asphalt on the west side of bridge Installation of handrails Continue with asphalt on east side of bridge First lift of base completed. Will place the second layer tomorrow Read more
4421 City of Fulton 2nd st Bridge Get link Facebook X Pinterest Email Other Apps May 25, 2023 Pouring sidewalk for the South west side of Oak St Excavating south east side of oak St getting ready for concrete Read more
4421 City of Fulton 2nd St Bridge Get link Facebook X Pinterest Email Other Apps May 25, 2023 Pouring barrier walls for bridge Pouring retaining wall on South east Oak st Continue with barrier walls Read more
4421 City of Fulton 2nd Bridge Get link Facebook X Pinterest Email Other Apps May 18, 2023 Setting forms for curb Curb poured and approach Read more
4421 City of Fulton 2nd St Bridge Get link Facebook X Pinterest Email Other Apps May 16, 2023 Preparing for concrete pour Poured curb for drive Excavating roadway on Oak and second Street Cutting concrete for construction joint Read more
4421 City of Fulton 2nd St bridge Get link Facebook X Pinterest Email Other Apps May 12, 2023 Rebar is tied waiting on concrete Started concrete pour Form for curb and gutters Pour curb and gutter Read more